LUCERO DEVELOPMENT SERVICES

Saving the Middle Class — When the Process Makes Housing More Expensive — Part IV

When Zoning Allows the Housing but the Development Process Still Makes It Expensive

By John R. Lucero

November 10, 2026

Colorado’s housing debate has spent considerable time on zoning, and for good reason. A townhome cannot be built where the zoning code does not allow it.

But permission to build is only the first step.

Once a project is legally possible, the next question is whether it can move through subdivision, utilities, building review, fire review and permitting on a schedule and at a cost that still allows the finished homes to reach middle-income buyers.

That challenge is not unique to Denver. It exists in communities across the Front Range, on the Western Slope, in mountain towns and in smaller Colorado cities where a project may involve fewer agencies but have even less ability to absorb delay.

Denver provides a useful case study because it is actively reconsidering its middle-housing rules. But the larger lesson is statewide: process is part of price.

A month of additional review is not free. Neither is a second utility redesign, an uncertain subdivision path, repeated permit resubmittals or a code interpretation that arrives after construction documents are substantially complete.

Each adds professional fees, financing carry, construction escalation and risk. Individually, those costs may appear manageable. Together, they can determine whether a middle-market townhome can actually be built.

Zoning Reform Is Only the Beginning

Denver’s Unlocking Housing Choices initiative illustrates the next challenge.

The first phase has focused largely on what types of housing the zoning code should allow. The City has indicated that a later phase will also examine development-review procedures for smaller residential projects. [1]

That distinction matters.

Changing zoning may create the legal capacity for additional homes, but those homes still must make their way through the development system. If the approval process remains unpredictable, expensive or poorly coordinated, some of the new zoning capacity may never become actual housing.

The same issue applies outside Denver.

A community may decide that duplexes, townhomes, cottage developments or other forms of middle housing belong in appropriate neighborhoods. That does not mean every project should receive automatic approval or avoid normal safety and infrastructure standards.

It does mean the review process should reflect the scale and complexity of the project.

A four-home infill development should meet applicable building, fire, utility and infrastructure requirements. But it should not automatically inherit the administrative complexity of a major subdivision or a large multifamily development when the impacts are materially different.

Process Is Part of the Development Budget

Development budgets usually identify land, construction, professional services, financing, fees and developer return.

Time runs through every one of those categories.

Land carry continues while plans are under review. Architects, engineers and attorneys remain engaged through resubmittals. Construction pricing can move while permits are unresolved. Equity remains tied up. Lenders price uncertainty into the capital structure.

Large projects can spread some of those costs across hundreds of units.

A four- or six-unit townhome development has only a handful of sale prices across which to distribute them.

That is why small-scale housing can be particularly sensitive to regulatory delay.

The objective should not be weaker standards. It should be clearer standards, fewer avoidable handoffs and more predictable decisions.

Predictability is itself an affordability tool.

Ownership Must Be Planned From the Beginning

Townhomes intended for individual ownership create issues that rental housing under common ownership may not.

Each home ultimately needs to be financeable, insurable and transferable.

That means developers need early answers about lot configuration, access, easements, common improvements, maintenance obligations and utility service.

A project should not reach the end of design before learning that its intended ownership structure requires substantial changes.

For example, a legal lot does not automatically have a workable utility plan. A recorded easement does not necessarily solve the same problem as an independent utility connection. A shared driveway may work physically but still require legal agreements acceptable to lenders and title companies.

Those questions should be addressed near the beginning of the development process.

If fee-simple ownership is the intended result, the developer should know early whether the proposed lots, access arrangements, utility systems and common improvements can support separately financed homes.

Late changes ripple through civil engineering, architecture, utilities, legal documents and financing.

That cost ultimately reaches the buyer.

Utilities Need to Be Reviewed as a System

Water, sanitary sewer, stormwater, electricity and other utilities are often controlled by different departments or service providers.

On the ground, however, they occupy the same site.

A requirement that appears reasonable when considered by one agency can force another system to move, triggering redesign and another review.

That is why early utility coordination is particularly important for infill and small ownership projects.

Before substantial design work is completed, a builder should be able to determine:

  • What existing services can be reused.
  • What must be replaced or upgraded.
  • Whether each separately owned home requires an independent connection.
  • Whether shared systems are permitted.
  • Where easements will be required.
  • Whether existing capacity receives credit.
  • Which improvements trigger additional fees or review.

The answers will vary by community and utility provider.

That is appropriate. Colorado does not need identical infrastructure rules in every jurisdiction.

It does need predictable rules.

A townhome project in Grand Junction will not have the same infrastructure conditions as one in Denver, Fort Collins or a mountain community. But developers in each place should be able to identify the applicable requirements before committing significant land and capital.

Building and Fire Review Need a Small-Project Lens

Building and fire codes serve essential life-safety purposes. Middle housing should not be exempt from those protections.

The issue is predictability.

A change in building classification can affect fire separation, sprinklers, egress, accessibility, structural systems and utility sizing. If those decisions occur late in the process, a relatively small project can face substantial redesign.

For a large development, those costs may be spread across many units.

For four townhomes, they cannot.

Communities pursuing middle housing should therefore consider publishing representative code pathways for common building types and identifying the decisions that materially change the applicable requirements.

Pre-approved or pattern designs can help, but they are not a complete solution.

A standard building plan does not eliminate site-specific issues such as grading, drainage, utilities, access, lot configuration or fire response.

The better objective is a repeatable approval framework in which the major questions are known before a developer completes the design.

Fees Should Be Knowable Before the Land Is Bought

A developer can underwrite a known fee.

An unknown fee becomes a contingency.

Contingencies raise the cost the project must support.

Water and sewer charges, building permits, subdivision expenses, inspection fees and required infrastructure improvements should therefore be reasonably calculable before a developer commits to a site.

This becomes especially important when an existing home or utility connection will remain.

Does previously paid capacity receive credit?

Does dividing a parcel create a new system charge?

Can an existing service remain for one home while new connections serve the others?

Those are technical questions, and the answers will differ among jurisdictions and utilities.

The policy recommendation is simpler: answer them early enough to matter.

The most expensive answer is often the one that arrives after the project has already been designed and financed around a different assumption.

Housing Hub Colorado Shows the Value of Removing Duplication

Colorado is already applying this principle on the financing side of affordable housing.

Housing Hub Colorado brings state agencies, CHFA and participating local governments together to better align application materials, narrative questions and funding timelines. Its next phase develops a common application and contemplates expansion to additional programs, including homeownership. [3]

Housing Hub is not a middle-market zoning program, and it should not be described as one.

Its significance here is procedural.

The participating agencies have recognized that multiple applications requesting the same information consume time and money without producing additional housing.

The solution is coordination: one set of core information, aligned requirements and a more predictable schedule.

That same principle applies to small-scale ownership housing throughout Colorado.

Whether a project is in a Front Range suburb, a Western Slope community, a mountain town or Denver, a builder should not have to discover sequentially that planning, transportation, utilities, fire, building review and other agencies are each waiting on a related decision from someone else.

Where reviews can run concurrently, they should.

Where one decision must come before another, the sequence should be clear at the beginning.

Local governments will retain different codes, infrastructure conditions and community priorities. But the underlying development principle is universal: predictability reduces cost without requiring communities to surrender local control.

Small Projects Need a Predictable Review Path

Communities pursuing middle housing should consider a defined review path for qualifying small projects.

The point would not be automatic approval.

It would be an exchange: project simplicity for process certainty.

A qualifying project might involve a limited number of homes, an existing residential context, no major variance, known utility capacity, conventional construction and compliance with published access and ownership requirements.

In return, the local review process could provide:

  • One coordinated intake identifying all required approvals.
  • Early confirmation of subdivision, access and utility strategy.
  • Concurrent review where agency decisions are not dependent on one another.
  • Published review periods.
  • Consolidated comments rather than repeated serial reviews.
  • Clear code interpretations for common middle-housing forms.
  • A process for resolving conflicting agency requirements.
  • A final checklist that builders, lenders and title companies can rely upon.

Projects involving unusual infrastructure, major discretionary approvals, environmental constraints or significant public impacts would remain on the appropriate full review path.

The goal is not to make every development simple.

It is to stop making simple developments unnecessarily complicated.

Measure the Cost of Time

Communities should also measure how long housing approvals actually take.

That means more than reporting an average permit time.

A useful analysis should identify where the time occurs:

  • Initial completeness review.
  • Agency review.
  • Applicant response.
  • Utility coordination.
  • Interagency conflict resolution.
  • Final permit issuance.

The purpose is not to assign blame.

Good data can distinguish a staffing problem from an incomplete application, a confusing code provision from an infrastructure limitation, and an unusual project from a recurring system problem.

It also allows communities to see whether reforms are working.

If policymakers want middle housing to become a meaningful ownership option, they should know how much time—and therefore carrying cost—the development process adds to a typical project.

Predictability also benefits neighbors and the public.

Clear standards reduce the need to negotiate basic requirements project by project. Published processes identify when public participation occurs and what decisions remain discretionary.

Speed and accountability are not opposites when the rules are established in advance.

Colorado Needs Delivery Reform Alongside Zoning Reform

Zoning reform can create legal capacity for additional housing.

That is necessary.

It is not sufficient.

The practical test is whether a builder can identify the zoning, ownership structure, utility requirements, code path, fees and review schedule before committing substantial land and capital.

Can related agencies identify conflicts before those conflicts become expensive redesign?

Can a small project move through review on a timeline proportionate to its complexity?

Can a local government protect public safety, infrastructure and neighborhood interests while still providing a predictable development path?

If the answer is yes, zoning reform has a better chance of becoming actual homes.

If the answer is no, additional zoning capacity may exist largely on paper while the finished product remains too expensive for the households the policy was intended to serve.

Denver has an opportunity to test these ideas as it continues its middle-housing work.

Other Colorado communities should develop approaches that fit their own markets, infrastructure and local priorities.

The objective is not one statewide zoning code or one prescribed development model.

It is a more practical principle: allow the housing that makes sense locally, protect the public interest, and make the path from approval to construction predictable enough that middle-market homes can actually be delivered.

Process is part of price.

Housing policy should treat it that way.

Sources

  1. Denver Community Planning and Development — Unlocking Housing Choices
  2. Denver HUD Pathways to Removing Obstacles to Housing (PRO Housing)
  3. Housing Hub Colorado — cross-agency partnership among the Colorado Department of Local Affairs, Colorado Housing and Finance Authority, Colorado Office of Economic Development and International Trade, and Denver Department of Housing Stability.
  4. Lucero Insights: Middle-Market Townhomes and Shared Equity — Part I
  5. Lucero Insights: The Economics of Attainable Homeownership — Part II
  6. Lucero Insights: Connecting Land, Zoning and Capital — Part III
  7. Denver Community Planning and Development — Unlocking Housing Choices Feasibility Analysis
  8. Denver Water — 2026 System Development Charges
  9. Denver DOTI — 2026 Sewer Permit Fees

About the Author

John R. Lucero is founder and principal of Lucero Development Services, Inc. and has more than 30 years of experience in real estate and economic development, including service as Deputy Director of Denver’s Office of Economic Development and as a Denver Water Commissioner. His work focuses on housing, public-private partnerships, development finance and public policy.